Evaluations - Evaluation of Infrastructure Canada's Economic Action Plan Initiatives - Chart 11 - text description
Chart 11 – Per cent of Infrastructure Stimulus Fund projects and value of projects substantially completed by March 31st, 2011 by materiality (total eligible costs) – Text Description
Bar graph showing the percentage of Infrastructure Stimulus Fund projects and value of projects substantially completed by March 31st, 2011 by materiality (total eligible costs).
Value of projects substantially completed by March 31st, 2011 |
% of Project | % of Funding |
---|---|---|
< $75K | 88% | 88% |
$75K-$150K | 85% | 87% |
$150K-300K | 78% | 77% |
$300K-$600K | 75% | 75% |
$600K-$1.5M | 70% | 70% |
$1.5M-$3M | 63% | 65% |
$3M-$5M | 51% | 53% |
$5M-$15M | 34% | 33% |
$15M-$30M | 15% | 15% |
$30M + | 11% | 12% |