Chart 20 – Reasons for Delays – Text Description

Bar graph showing the different reasons for delays identified by funding recipients of the Infrastructure Stimulus Fund, the Communities Component Top-Up, the National Recreational Trails, and all combined programs.

Programs Reasons for Delays Weighted % of Respondents
Infrastructure Stimulus Fund Expansion in project scope 54%
Tendering took longer 48%
More planning needed 42%
External factors 83%
Resourcing issues in my organization 34%
Timeliness of project approval 25%
Communities Component Top-Up Expansion in project scope 23%
Tendering took longer 15%
More planning needed 10%
External factors 8%
Resourcing issues in my organization 1%
Timeliness of project approval 20%
National Recreational Trails Expansion in project scope 15%
Tendering took longer 31%
More planning needed 28%
External factors 75%
Resourcing issues in my organization 8%
Timeliness of project approval 63%
All Expansion in project scope 50%
Tendering took longer 44%
More planning needed 39%
External factors 83%
Resourcing issues in my organization 30%
Timeliness of project approval 25%