Programs | Reasons for Delays | Weighted % of Respondents |
---|---|---|
Infrastructure Stimulus Fund | Expansion in project scope | 54% |
Tendering took longer | 48% | |
More planning needed | 42% | |
External factors | 83% | |
Resourcing issues in my organization | 34% | |
Timeliness of project approval | 25% | |
Communities Component Top-Up | Expansion in project scope | 23% |
Tendering took longer | 15% | |
More planning needed | 10% | |
External factors | 8% | |
Resourcing issues in my organization | 1% | |
Timeliness of project approval | 20% | |
National Recreational Trails | Expansion in project scope | 15% |
Tendering took longer | 31% | |
More planning needed | 28% | |
External factors | 75% | |
Resourcing issues in my organization | 8% | |
Timeliness of project approval | 63% | |
All | Expansion in project scope | 50% |
Tendering took longer | 44% | |
More planning needed | 39% | |
External factors | 83% | |
Resourcing issues in my organization | 30% | |
Timeliness of project approval | 25% |