Evaluations - Evaluation of Infrastructure Canada's Economic Action Plan Initiatives - Percentage of Infrastructure Stimulus Fund projects complete – Text Description

Percentage of Infrastructure Stimulus Fund projects complete – Text Description

Bar graph showing the percentage of Infrastructure Stimulus Fund projects completed within Economic Action Plan timelines. The chart shows that about 67% of projects were complete by the initial deadline of March 31, 2011. By the time the program ended on October 31, 2011, 97% of projects were complete.