The New Champlain Bridge - Detailed Project Timelines

Graphic of the project timeline. Read a text description of the image below.

Text Description

Timeline showing the progression of work to build a new bridge for the St. Lawrence in Montréal, as follows:

Stage 1 – Request for Qualifications, Spring 2014

RFQ release, March 17, 2014
Information Session and Site Visit, March 31 and April 1, 2014
Industry Day, March 31, 2014
End of Enquiry Period, April 22, 2014
Response Submission Deadline, May 7, 2014
Response Evaluation Completion, June 2014

Stage 2 – Request for Proposals, Summer 2014 to Summer 2015

RFP Release to Proponents, July 2014
Technical Proposal Submission Deadline, February 2015
Financial Proposal Submission Deadline, Early April 2015
Announce Preferred Proponent, Late April 2015
Financial Close, June 2015
Signing of the Project Agreement, June 2015

Design-build phase, Summer 2015 to 2020

New Bridge for the St. Lawrence in service, December 2018
Substantial Completion, 2019

Operating phase, 2020 to 2050