New Bridge for the St. Lawrence - Presentation: Information session on Hydro-Québec tower relocation - Project Timelines
Text Description
Timeline showing the progression of work to build a new bridge for the St. Lawrence in Montréal, as follows:
Stage 1 – Request for Qualifications, Spring 2014
RFQ release, March 17, 2014
Stage 2 – Request for Proposals, Summer 2014 to Summer 2015
RFP Release to Proponents, July 2014
Present
Technical Proposal Submission Deadline, February 2015
Financial Proposal Submission Deadline, Early April 2015
Announce Preferred Proponent, Late April 2015
Financial Close, June 2015
Design-build phase, Summer 2015 to 2020
New Bridge for the St. Lawrence in service, 2018
Operating phase, 2020 to 2050
Substantial Completion, 2020